The Municipal Water District of Orange County (MWDOC) is seeking bids from qualified firms (Contractor) to complete the MWDOC Electrical System Rehabilitation Project (the “Project”). The project in general consists of increasing electrical service to the MWDOC administration building from 350A to 600A; installation of new circuit breaker panels, installation of a new 112.5KVA transformer, installation of a manual transfer switch and a generator tap box for emergency generator power, and removal and demolition of old electrical equipment and appurtances. The building will remain in operation during construction and requires a coordinated weekend switch over to the new feed to allow for continued operations. Following the switchover to the new 600A feed, the old electrical equipment will be removed and deposed of.

A “NON-MANDATORY” Pre-Bid Conference is scheduled for May 14, 2019 at 8:30 AM to review the Project’s existing conditions at 18700 Ward St. Fountain Valley, CA 92708.